- Location: Bedford Park, IL
- Contract Value: $6,828,528
- Owner: Village of Bedford Park
- Engineer: Baxter and Woodman
- Delivery Method: Design-Bid-Build
A new pumping station building, including water piping up to 54-inch diameter, chlorine gas equipment, heating, plumbing, instrumentation and controls, site improvements and restoration, approximately 1,050 feet of 36-inch diameter water main, 180 feet of 48-inch diameter water main, 55 feet of 54-inch diameter suction pipe, site improvements, installation of two 250 HP vertical pumps, four 300 HP vertical pumps, and a prefabricated meter vault. Key aspects involve scheduling and coordination with the owner to keep the plant in operation during the improvement stages.