PROJECT DETAILS

  • Location: Highland Park, IL
  • Contract Value: $22,355,647
  • Owner: City of Highland Park
  • Engineer: Camp, Dresser & McKee, Inc.
  • Delivery Method: Design-Bid-Build

PROJECT DESCRIPTION

Significant improvements to the water treatment plant were made to increase the drinking water output from 21 million gallons per day (MGD) to 30 MGD using membrane filtration, a newer treatment technology considered the wave of the future for drinking water purification.

This complex project included construction of a membrane treatment facility and installation of membrane equipment; upgrade of the raw water pumping station; construction of new electrical switchgear room; new engine generator facility and installation of diesel generators; improvements to the existing residual solids building; renovations to the existing chemical facilities; and construction of site improvements.